Hydro One, in collaboration with First Nation partners, is undertaking a Class Environmental Assessment (EA) for a proposed electricity transmission project connecting the Hanmer Transformer Station in Sudbury to the Essa Transformer Station near Barrie, ON.
The proposed priority project includes:
- A single-circuit, 500-kilovolt (kV) transmission line that will span approximately 300 kilometres from the Hanmer Transformer Station (TS) in Sudbury, to the Essa TS near Barrie, including facility expansions at both the Hanmer TS and Essa TS, and the construction of a new midpoint station. The line is anticipated to be in service in 2032.
- Completion of development work on a second new single-circuit, 500-kV transmission line. A recommended in-service date for the second line will be determined by the Independent Electricity System Operator.
What does this mean for Oro-Medonte?
Proposed transmission routes pass through the Township of Oro-Medonte. Hydro One is currently evaluating route alternatives and considering environmental, technical, cultural and community impacts.
No preferred route has been selected at this time. Hydro One anticipates presenting its preferred route in 2027.
Residents, property owners, and businesses are encouraged to review the proposed routes, learn about potential impacts, and share their feedback during the consultation process.
Community Open House
Hydro One will be hosting an in-person Community Open House in Barrie, ON:
- Date: Wednesday, December 2nd
- Time: 3:30 p.m. - 7:30 p.m.
- Location: General John Hayter Southshore Community Centre
- Address: 205 Lakeshore Drive, Barrie, ON
Representatives from Hydro One will be available to provide information, answer questions and gather community feedback.
Virtual Information Sessions:
Residents may also participate in virtual sessions:
- Thursday, November 26, 2025 | 6:00 p.m. - 7:00 p.m.
- Tuesday, December 8, 2026 | 6:00 p.m. - 7:00 p.m.
*Registration is available through Hydro One's Project Website
Hydro One: Sudbury-Barrie Transmission Line Website Sudbury-Barrie Transmission Line Interactive Map Sudbury-Barrie Transmission Line Alternative Routes Map
Review the Proposed Routes and Provide Feedback
Residents can view the proposed transmission routes, access the interactive project map, and obtain additional information by visiting HydroOne.com/SBTL.
For project-related inquiries, please contact Hydro One directly:
- Email: Community.Relations@HydroOne.com
- Telephone: 1-877-345-6799
The Township of Oro-Medonte is sharing this information to ensure residents are aware of the proposed project and opportunities to participate in the consultation process.
Sign up for our Council Highlights & Township Updates Newsletter
Stay up-to-date with Council meetings, important topics of discussion, and relevant information by subscribing to the Council Highlights & Township Updates eNewsletter!